| The
                 In compliance with Section-3 of the Electricity Act-2003 the Central Government notifies the National Electricity Policy. The Section 3(1) of this Act-2003 requires the Central Govt. to formulate, inter alia, the National Electricity Policy in consultation with Central Electricity Authority (CEA) and State Govt. The plan prepared by CEA and approved by Central Govt. can be used by prospective generating companies, transmission utilities as reference document. 
 The Transmission System requires adequate and timely investments and also efficient and coordinated action to develop a robust and integrated power system for the country. Keeping in view the massive increase planned in generation and also for development of power market, there is need for adequately augmenting transmission capacity in order to avoid mismatch between generation capacity and transmission facilities. The Planning of the Network expansion and its implementation program is most essential for the organization for its future growth.
 
 The Directorate of Corporate Planning was created in GRIDCO during the year 1995. The Corporate Planning was assigned with the following main activities.
 
 
 
                  
                    | 
                      
                      Long Term financial projection and overall perspective planning.
                      
                      Co-ordination of reform-restructuring  process.
                      
                      Co-ordination with project Management Unit.
                      
                      Liaison with external agencies like Govt. of Orissa, CEA, World Bank etc on Corporate Policy and reform/restructuring.
Further, after 01.04.1997, the activities of the Corporate Planning were modified as under.
                      
                      Monthly returns on various planning aspects to Govt. of Orissa and Govt. of India.
                      
                      Returns on various planning aspects to Central Electricity Authority and  Orissa   Electricity Regulatory Commission.
                      
                      Compliance to questionnaire of the State Legislative Assembly/Parliamentary  affairs.
                      
                      Any other works as and when required.
 |  
                Plan and Operate the Transmission System so as to ensure that transmission system built, operated and maintained to provide efficient, economical and coordinated system of Transmission and meet the overall Performance Standard.
 Development of a well coordinated transmission system in the back drop of formation of Strong National Power Grid as a flag ship, endeavor to steer the development of Power System on planned path leading to cost effective fulfillment of the objective of “Electricity to All” at affordable price.
 
 Subsequently from 01.04.2005  Orissa Power Transmission Corporation Ltd (OPTCL) is engaged in the business of Transmission of electric energy in the state of Orissa and OPTCL has been notified as State Transmission Utility (STU).
 
 The Long Term Planning Cell (LTPC) which was created in February-2000 under Corporate Planning branch of OPTCL deals with to carry out specific long Term Planning Activities (the period of 3 months to 10 years ahead). The LTPC plays an important role in supporting the corporate level planning process by supplying data, information support and conducting system studies.
 
 
                  
                    | Planning Process  |  
                    | 
                      
                      Preparation of data.
                      
                      Detail load Forecasting . (The forecast of long term demand for electricity is  a fundamental prerequisite for the development of a secure and economic power  system. The said forecast is being revised in each year and submitted  to OERC as per Grid Code taking due care of new policies of Govt. and changes in the socio-economic trends.)
                      
                      Locating load centers
                      
                      Identifying sub-station location and voltage class.
                      
                      Staging study for base year, intermediate year and horizon year
                      
                      The load flow study is prepared for different condition of generation schedule  including Short Circuit study, transient stability analysis.
                      
                      Development of upstream/Down stream network
                      
                      Consideration of addition of system elements  to avoid system constraints and to   meet the planning criteria. |  
                    | 
					
					Overall the planning is based on the guidelines as  prescribed by Central Electricity Authority and Regulatory Commission. 
 The  activities to be carried out has been laid down in  the standard planning procedures (SPPs)  approved by GRIDCO in December’2000. Some of these are statutory in nature i.e.  needs to be submitted to OERC within a prescribed time frame, The said SPP are  being followed by OPTCL.
 
 
 
 
 |  
                    | THE WORK EXECUTED BY LTPC  SO-FAR AS FOLLOWS;. |  
                    | (1)   System Study.System studies for the first time for any  existing/new users who are connected/proposed to be connected to the Orissa  Grid net work, conducting load flow study, shut circuit study, Transient Study  analysis in different conditions. As on to-day, this branch has conducted  almost 150 nos system studies for some users on their request on prepaid basis.
 (2)   Long Term Demand Forecast.      Long Term Demand Forecast (LTDF) report for coming 10years is being  processed in each year based on the data of coming 5 years received from the  DISCOMs. The LTDF report for the period 2010-19 is  submitted to Hon’ble OERC during May’10 for  kind approval.
 (3)   Long Term Perspective Transmission  Plan.
 OPTCL  ensures development of an effective and economical system of Intra-State and  Inter-State transmission lines for smooth flow of electricity from generating  station to Load center.
 The  infrastructure of  OPTCL network is as  follows.
 
                        95nos. of Grid Sub-Stations with transformation capacity of 8845MVA.10902Ckt. KMs of transmission lines of 400KV,220KV and 132KV rating. The present peak demand of  the state is around 3000MW, which is handled by the existing network of  equipment of the system. To improve the low voltage problem in some of the Grid  Sub-Stations, action has already been initiated to install 275MVAR shunt  capacitors.
 According to the long term  demand forecast, the peak demand of Orissa at the end of 11th and 12th  plan period will be to the tune of 4459MW and 6363MW respectively. Besides the  above projection , in the mean time a number of IPPs have signed MOUs with  Govt. of Orissa to install power plants in Orissa. It is expected that at the  end of 12th plan period the quantum of power generated by these IPPs  will be of 20000MW and Orissa will avail the state share of 25% i.e. about  5000MW . Therefore Orissa Transmission System needs to be planned to handle the  upcoming load which will cater to the load requirement of different up-coming  industries and schemes like REC,RGGVY and BGJY.
 
 Planning is required for a healthy transmission  system to extend uninterrupted, quality and reliable power supply. Alternative  source of supply is to be made available at all Grid Sub-Stations to avoid  total power failure in the region due to fault in single source of supply. All  the Grid Sub-Stations is to operate in a ring arrangement. In view of the above  , OPTCL has prepared a comprehensive system planning of its network, by M/S  PRDC Ltd., Bangalore. Planning is made to prevent overloading wherever possible  by load diversion and taken up innovative measures for system loading of its  existing network. Effective utilization of new lines and their impact on  transmission loss is being taken care.
 
 
   |  
                    | Long Term  Transmission Plan for 11th Plan Period. |  
                    | Integrated Transmission  Planning of OPTCL network for 11th plan period has been prepared  taking the system peak demand of 4459MW (including 968MVA load of RGGVY  &BGJY) and additional generation of 1264MW as state share from  following 4nos. upcoming IPPs. |  
                    | 
                      
                        | Sl. No. | Name of    IPPs | Location of    Project | Installed    Capcity | Orissa  StateShare(25%)
 |  
                        | 1. | Sterlite Energy (P) Ltd. | Jharsuguda | 2400MW | 600MW |  
                        | 2. | GMR Energy (P) Ltd | Dhenkanal | 1050MW | 263MW |  
                        | 3. | KVK Nilachal (P) Ltd | Athagarh | 600MW | 150MW |  
                        | 4. | Monnet Ispat & Energy    (P) Ltd. | Angul | 1005MW | 251MW |  
                        |                                                                 TOTAL | 5055MW | 1264MW |  |  
                    |  |  
                    | The proposed infrastructure  additions to meet the peak demand of 4459MW are as follows.(i) 400KV Grid S/S – 5nos.    (Keonjhar,Lapanga,Duburi,Bolangir & Uttara)
 (ii)220KVGridS/S–17nos. (Karadgadia,Paradeep,Puri,Cuttack,Bhadrak,Nuagaon,Dhenkanal(new),Kuanrmunda,Kesinga,Barbil,
 Uttara,Bolangir(new),Keonjhar,Banai,  Laxmipur, Dhamara and Hindol Road)
   
                        !32KVGridS/S–32nos.                               (Koraput,Nawrangpur,Baliguda,Nilagiri,Marsaghai,Sakhigopal,Tangi,  Barpali,Karanjia,Udala,Basta,Phulnakhara,Badagada,
 Anandpur,Purusottampur,Nuapada,Dabugaon,Chandpur,Padampur,
 Kuchinda,Bhawanipatna,Boud,Banki,Kalunga,Barbil,Karadgadia,Uttara,Bolangir(new),  Dhenkanal(new) Kuanrmunda,
 Dhamara and OCL (switching station)
Reactive power compensation by installing Shunt Capacitor of 760MVAR in  different Grid S/S of OPTCL.Associated Transmission Lines (a) 400kV Transmission Lines     -        2nos  -        135 Kms.(b) 400kV LILO Lines                  -        6nos.
 (c)220kV Transmission Lines      -        14nos.         -648.59Kms.
 (d) 220kV LILO Lines                  -        10nos.
 (e)132kV Transmission Lines      -        29nos.         992.91Kms.
 (f) 132kV LILO Lines                            -        21 nos.
 
 
 
 
 |  
                    | Augmentation and Addition of Transformer Capacity with 3rd  Bay of Existing Grid S/S
                        
                          Besides the above, the  proposal for capacity addition with augmentation and addition of transformer  capacities with 3rd bay in 50 nos. existing Sub-Stations with  transformation capacity by 2612.5MVA. Subsequently to meet the additional load  of RGGVY and BGJY further 7nos. of transformers required to be commissioned at Jaynagar,Junagarh,Bhadrak,Karanjia,Kamakshyanagar,Rajgangpur  and Budhipadar Grid Sub-Stations.
 Long Term  Transmission Plan for 12th Plan Period.          In  addition to 11th plan period, integrated Transmission Planning of  OPTCL network for 12th plan period has been prepared taking the  system peak demand of 6363MW and additional generation of 4669MW as state share  from 4nos. IPP taken in 11th plan period along with  following 11nos. upcoming IPPs |  
                    | 
                      
                        | Sl. No. | Name of    IPPs | Location of    Project | Installed    Capcity | Orissa  StateShare(25%) |  
                        | 1. | NavaBharat Power Pvt.Ltd. | Dhenkanal | 1050MW | 262.5MW |  
                        | 2. | Jindal India Thermal Power    Ltd. | Angul | 1200MW | 300MW |  
                        | 3. | Lanco Babandh Power Pvt.    Ltd. | Dhenkanal | 2640MW | 660MW |  
                        | 4. | Visa Power Ltd. | Athagarh | 1000MW | 250MW |  
                        | 5. | Bhusan Energy (P) Ltd. | Angul | 2000MW | 500MW |  
                        | 6. | CESC Ltd. | Dhenkanal | 1000MW | 250MW |  
                        | 7. | Tata Power Company Ltd. | Marthapur, Cuttack | 1000MW | 250MW |  
                        | 8. | Essar Power (Orissa) Ltd. | Angul | 1000MW | 250MW |  
                        | 9. | Mahanadi Abban Power Co. | Talcher, Angul | 1030MW | 257.5MW |  
                        | 10. | IND-BHARAT Energy Ltd. | Jharsuguda | 700MW | 175MW |  
                        | 11. | Aarati Steels Ltd. | Ghantikhal,Cuttack | 1000MW | 250MW |  
                        |                                            TOTAL | 13,620MW | 3405MW |  |  
                    |  |  
                    | In addition to  the projects proposed in 11th plan period the following  infrastructure additions have been kept to meet the peak demand of 6363MW. 
                        132/33kV Grid S/S at Olaver132/33kV Grid S/S at Titlagarh (iii)    Reactive power compensation by installing Shunt Capacitor of  200MVAR at Duburi and Bhadrak region and  150MVAR at Berhampur region.(iv)    Associated Transmission Lines
 132kV LILO Lines         -        2nos.
 
 
 Prioritization Study of  Up-coming Projects under 11th Plan period
 Subsequently, for the purpose of  implementation of the proposed projects under Transmission Planning of 11th  plan period, System Study work has  been assigned  to M/S PRDC Ltd. Bangalore to conduct the Prioritization study by phasing the  total upcoming projects in coming 4years i.e. during  2009-10.2010-11,2011-12,2012-2013.The first report of prioritization from M/S  PRDC is awaiting.
 Proposal for Power Evacuation from Up-coming IPPs  through 400KV Ring System
 In the mean  time 33nos. of IPPs have planned to install their power plant in Orissa  including the above 15nos.. It is expected that at the end of 2020 the quantum  of power generated by those IPPs. will be to the tune of 46,070 MW and  Orissa will avail its state share about 25% .
 OPTCL has also  initiated necessary action for evacuation of   state share power from up-coming IPPs through 5nos. STU Sub Pooling  Stations at Jharsuguda,Bamur,Nisa/Boinda, Angul and Khuntuni,  which will be connected to 3nos. CTU (765KV) pooling stations at Jharsuguda,  Angul and Dhenkanal to be connected by PGCIL for inter-state long term open  access.
      The above Sub-Pooling Stations will be a part of the 400KV Ring  system with 10nos. 400KV Grid Sub-Stations and 1482 KMs of 400KV lines.The  proposal of 400Kv ring system has already been apprised to CEA and for the  feasibility of the scheme the comprehensive study work has been assigned to M/S  PRDC Ltd.  It will facilitate the state  to evacuate the surplus power and to utilize the required power effectively and  transmit these power through available downstream network. |  
                    |  |  
                    |  |  |